The roof of the CMC is completed, and the new shingles on the sanctuary building is about 60% complete.  Completing earthwork is being done on the retention basin, preparing for grass seed.  The new pump station connections are being completed.  Concrete has been poured in the discipleship building, lower level, and bracing of the metal roof trusses, as well as preparation for metal studding is underway.

OLYMPUS DIGITAL CAMERA OLYMPUS DIGITAL CAMERA OLYMPUS DIGITAL CAMERA OLYMPUS DIGITAL CAMERA OLYMPUS DIGITAL CAMERA OLYMPUS DIGITAL CAMERA OLYMPUS DIGITAL CAMERA OLYMPUS DIGITAL CAMERA OLYMPUS DIGITAL CAMERA OLYMPUS DIGITAL CAMERA OLYMPUS DIGITAL CAMERA OLYMPUS DIGITAL CAMERA OLYMPUS DIGITAL CAMERA OLYMPUS DIGITAL CAMERA