Construction Update – November 14, 2013

The painting and pre-construction work in the CMC is nearly complete, and the moving of the playground will begin, along with the sidewalk and entry construction on the south side of the CMC.  Due to some questions regarding geo-technical work near the north CMC entrance, the bidding and date schedule has been revised to the following:

January 9 – Contractors’ bids are due in the church office

January 14 – Bids from GCs opened / reviewed by the Construction Planning Team (CPT)

January 15 – Board of Administration (BOA) reviews CPT’s recommendations regarding the bids and the proposed General Contractor

January 19 – Society Meeting following evening worship to vote on the CPT / BOA recommendation

All full members, please mark your calendar for that January 19 meeting.  Of course, all church attendees are welcome to attend the meeting.